| DAY |
Morning (0900 to 1200 Hrs) |
Afternoon (1300 to 1630 Hrs) |
| 1st. |
Basic Principles of Automatic Control
Terminology and symbols final control element and valve positioner
Principles of current to pneumatic converter |
Laboratory work :
1) Pilot Plant
2) Current to pneumatic converter calibration
3) Stripping & assembly of valves
4) Valve positioner calibration |
| 2nd. |
Flow measurement
Temperature measurement
Level measurement
Pressure measurement |
Laboratory work :
Pilot Plant |
| 3rd. |
Process characteristics
Modes control |
Laboratory work :
Process characteristics
Controller action - Open Loop |
| 4th. |
Controller tuning |
Laboratory work :
PID control response
Optimum PID setting
|
| 5th. |
Distributed control system appreciation |
Laboratory work :
Basic operation of a distributed control system Test |