Yokogawa Plays Key Role in Khurais Project - Oil & Gas News

Descarcă (1.9 MB)

Yokogawa Plays Key Role in Khurais Project

Partnering with Saudi Aramco, Yokogawa is providing local project execution including testing and implementing a continuing policy of Saudisation.

YOKOGAWA Middle East and Yokogawa Saudi Arabia Company have delivered top-of-the-line process control systems for the Khurais central producing facilities. This is a key project providing Saudi Aramco with a fully integrated world class crude oil processing and stabilising facility.

Khurais central processing facility project

The Yokogawa process control system was selected for the Khurais central processing facility project in August 2006

Partnering with Saudi Aramco, Yokogawa is providing local project execution including testing and implementing a continuing policy of Saudisation.

In addition to several other challenging initiatives in the regional energy sector, Yokogawa is playing a pioneering role in Saudi Aramco's Khurais central producing facility. This plant, the biggest in Saudi Arabia, is being designed to produce 1.2 million barrels per day (mbpd) of stabilised Arabian Light (AL) crude blend from the three fields with an approximate water cut of 30 per cent.

Khurais Central Processing Facility Project

Yokogawa Saudi Arabia Company building at Dhahran Techno Valley
Yokogawa Saudi Arabia Company building
at Dhahran Techno Valley

The Yokogawa process control system (PCS) for the Khurais central processing facility project was selected in August 2006 with Yokogawa working with its lump sum turnkey (LSTK) contractors. The project was divided into three sections and awarded to three major LSTK contractors.

The crude processing facilities and gas oil separation plant (GOSP)—1,2, 3 and 4 are executed by Snamprogetti, Italy.

The gas processing facilities Train—1 and 2, the inlet/outlet and storage/shipping facilities executed by Hyundai Engineering and Construction Co, Seoul, South Korea.

The water injection plants (Wips) and utilities are executed by Snamprogetti, Italy.

Yokogawa's scope of work included the supply, integration and testing as an integrated system at a single location with distributed control system (DCS)—Yokogawa, Saudi Arabia:

  • Emergency shutdown system (ESD);
  • Compressor control system (CCS);
  • Vibration/fin-fan monitoring system (VMS/FFVMS);
  • Smart valve monitoring system (SVMS/ SZVMS)—Yokogawa, Saudi Arabia;
  • Data acquisition and historisation system (DAHS);
  • Large screen TV (LSTV);
  • Asset management system (AMS)—Yokogawa, Saudi Arabia;
  • Alarm management system (ALMS)—Yokogawa, Saudi Arabia;
  • SCADA system—Yokogawa, Bahrain;
  • Burner management system (BMS);
  • Operator training simulator (OTS)—Yokogawa (Omega), Japan; and
  • Maintenance training system (MTS)—Yokogawa, Saudi Arabia

The plant, a large scale unit, includes 16,000 hardwired DCS inputs/outputs, 11,000 hardwired ESD inputs/outputs and 1,200 VMS points. YME deployed three teams catering to individual LSTK Contractors.

Yokogawa equipped the new facility of Yokogawa Saudi Arabia Company in Dhahran, to stage and test the entire system configuration in a fully integrated manner to achieve customer satisfaction.

Yokogawa's project teams comprised 60 engineers. Yokogawa also seconded its engineers at the LSTK contractor's location to assist and provide technical support in designing the system. Yokogawa, as part of its Saudisation commitment, recruited several engineers from Saudi Arabia for executing this project trained and integrated with Saudi Aramco and LSTK engineers during the engineering and testing phase.

In addition, Yokogawa is providing the Stardom as RTU's for the Wasia water wells which is integrated onto the Utility DCS. This scope contract was awarded in January 2008 and was executed in a six months period to meet the project requirement and schedule.

Yokogawa supplied state of the art consoles from Evans, Calgary to meet the modern design of central control room (CCR) planned by Italian architects with Snamprogetti, Italy.

The new CCR will control and monitor the GOSPs, stabilising facilities, water injection facilities, gas facilities and Scada from individual operator consoles.

All the equipment has been shipped to site and Yokogawa Middle East and Yokogawa Saudi Arabia are currently involved in the installation of the equipment and supporting the ongoing site acceptance tests (Sat).

Saudi Aramco and customer's feedback appreciate that Yokogawa transferred this project to inside Saudi Arabia since the project bidding and that it perfectly met Saudi Aramco's vision for local joint work with the vendor's project team.

Through the successful execution of these contracts from its base in Bahrain and new facility in Saudi Arabia, Yokogawa Middle East and Yokogawa Saudi Arabia have proven its capability to execute large-scale projects locally in the Middle East, to the fullest satisfaction of its customers.

Industrii

  • Petrol & Gaze

    Yokogawa has a wealth of experience in every part of the oil and gas business, from offshore and onshore facilities to pipelines, terminals, and deepwater operations. We provide solutions that enhance safety, ensure accurate and reliable operation, and increase plant efficiency.

    Vezi mai mult
  • Upstream

    The upstream industry includes offshore and onshore activities including wellhead automation, fractionation, completion, and separation to recover and prepare underground or underwater crude oil and natural gas.

    As petroleum is brought to the surface, it must be separated prior to transport. Primary and secondary separation stages commonly distribute gas flow, water flow, and oil flow in three phase separation. Gas movement requires pipeline and can include a fractionation process in the upstream stage prior to movement. Liquids can be placed into a tanks or pipelines and sent for processing, requiring accurate level measurements.

    Vezi mai mult

Produse & Soluții similare

  • SCADA Software (FAST/TOOLS)

    Originating as the Flexible Advanced System Techniques (FAST) project, FAST/TOOLS today is a comprehensive, fully-integrated SCADA application suite. Powerful and flexible, FAST/TOOLS serves installations ranging from 50-point unit processes to multimillion-point offshore production and pipeline systems that extend over thousands of miles.

    Vezi mai mult

Sus