Output/fuel: 1200 MW (2 × 600 MW), oil/gas fired
Owners: Tuas Power Pte Ltd, Singapore
Overview: The construction of Tuas Power Station started in the mid 1990s. The plant has steadily grown to be a significant player in the competitive Singaporean electricity market. Stage One of Tuas Power Station is equipped with the country's largest steam generators which are capable of producing 600 MW each.

Project

Tuas Power Station: Plant view
Safe and Efficient Power Plant Operation /
Tuas 1 Power Plant

Operation date: 1999
Project type: Greenfield site
Plant configuration:
Boilers: Babcock-Hitachi, Japan
Steam turbines: Hitachi, Japan
Overview: Yokogawa supplied an integrated distributed control system (DCS) for this plant's very large power generation units as part of the work in stage one. Yokogawa Electric Asia Pte. Ltd., Singapore produced the control system in Singapore and carried out all engineering work.

(Solutions/benefits)
Single source solution:
The plant successfully entered commercial operation on schedule and the plant owner attributed this in part to Yokogawa's good performance in delivering both products and services.
On-time commercial operation:
In addition to supplying Instrumentation & Control (I&C) equipment, Yokogawa handled system design/engineering, configuration, project management, commissioning services and maintenance. Operator/engineer training on a replica simulator and control room design were also provided.

System

Tuas Power Station: Full replica simulator
Full Replica Simulator

Control scope:
Coordinated boiler and turbine controls including:
burner management system
electrical distribution system
water and waste water treatment
other auxiliary plant controls

System equipment:
CENTUM CS
Computer station for unit performance calculation
Full scope, high fidelity training simulator
Sequence event monitoring system
Emergency shutdown system

(Replica Simulator Showcase)
A full scope, high fidelity training simulator was supplied by a wholly owned Yokogawa subsidiary, TechComm Simulation Pty Ltd. This simulator provides training in all aspects of operating complex plant systems. It has made a significant contribution in raising the skill levels of the highly motivated Tuas Power Station workforce.

Central Control Room (CCR) Design by Yokogawa

Tuas Power Station: Control Room Design

(CCR Design Showcase)
Yokogawa also designed the Tuas Power Station's Central Control Room, which has won praise from users for its good operating environment. Our CCR design methodology emphasizes the importance of sound ergonomic design in reducing operator errors and facilitating the smooth running and control of processes.

產業別

相關產品&解決方案

CENTUM CS

自從1993年推出以來,CENTUM CS在許多領域的工廠中得到了廣泛的應用,如: 石油冶煉、石化、化學、鋼鐵、有色金屬、金屬、水泥、造紙、食品和制藥、能源、天然氣和供水以及許多其他公共應用領域。

分散控制系統(DCS)

橫河電機的分散控制系統(DCS)實現了工業製程自動化控制,並增強了業務性能。超過10,000家工廠採用橫河DCS實現他們的生產目標。

×