Yokogawa Receives Award for Hot Cutover of BP Sharjah Plant DCS

BP logo
下载 (578 KB)

Executive Summary

BP Sharjah,UAE
BP Sharjah,UAE

BP Sharjah was established in the Emirate of Sharjah in 1978 and is one of the UAE's largest private producers and sellers of natural gas, condensate, and LPG. Its main gas production and processing facility about 40 km outside the city of Sharjah provides a key energy lifeline to the people of the UAE.

In 2007, BP initiated a project to replace the existing DCS at the Sharjah plant with a modern, reliable, and expandable system that is compliant with BP's engineering standards and Automation Blueprint and is supportable for at least the next 15 years.

The Challenges and the Solutions

In 2007, Yokogawa was selected by BP as main automation contractor (MAC) for a project to replace the Sharjah plant's existing Rosemount RS3 DCS with a Yokogawa DCS (CENTUM VP). This brownfield upgrade demanded sensitivity to the needs of the customer balanced with an innovative approach and a willingness to leverage the benefits of modern automation technology. The team set out to achieve this from the outset, specifying and designing a system that was in full compliance with BP's Automation Blueprint. It did so while planning to implement this system as a hot cutover - a phased signal-by-signal changeover to the new system with the plant remaining operational throughout.

A comprehensive user requirement specifications (URS) study and a FEED study were carried out by BP and Yokogawa in order to ensure that the Yokogawa system's capabilities closely matched the requirements of this complex BP facility. Taking an integrated team approach, Yokogawa Middle East worked closely with BP, ABB Engineering Services, and Maritime Industrial Services Company (MIS) with the shared goal of safely completing the upgrade and minimizing its impact on plant operations.

During the project, the team overcame various challenges and successfully delivered the job safely, on schedule, and on budget. A deep desire within BP and Yokogawa to learn lessons from previous projects was a catalyst in this project's success.

Some of the challenges that the team faced were:

  • A lack of up-to-date documentation
  • The need to integrate 32 subsystems spanning a variety of communication protocols
  • The requirement that the upgrade not interfere with normal operations at the critically important Sharjah plant

To address these challenges, numerous site surveys were conducted to collect and verify data on the existing plant facilities. A team of highly skilled engineers was deployed during the FEED study to examine the existing systems, and this team remained active until the commissioning of the new system was complete. Several unconventional decisions were made that included a decision to pre-test all the serial subsystems during the FEED stage to remove a known project scheduling risk.

Hot cutover
The BP Sharjah facility supplies gas to the power plants operated by the Sharjah Electricity Water Authority and is a critical part of the UAE's infrastructure. The plant is so important that even a one day shutdown was to be avoided. Hence, the commissioning was executed as a loop-by-loop hot cutover, requiring meticulous planning and execution. The cutover was executed successfully with no downtime, and saved an estimated 1,550 MMSCF of LPG and 60,000 barrels of condensate at present production rates.

Award from BP
At a function held at BP's Sharjah facility, four members of the Yokogawa team were commended by BP for outstanding contributions to the success of the project. The function was attended by executives from BP Sharjah and representatives of the Government of Sharjah.

Award from BP
Award from BP

Customer Satisfaction

Comment from Craig Fisher, Project Engineer:
"This was a complex job – minimising disruption to our customers meant replacing the control system while plant was running – not unlike performing a brain transplant while the patient was doing their normal day job. Brownfield upgrades such as this demand sensitivity to the requirements of the existing assets, and matching these with CENTUM VP's extensive capabilities was a fine balance. Yokogawa put a lot of effort into helping us define the scope, and deployed an exceptional team to deliver it. Several of the core team remained dedicated to the project until the last loop was commissioned. This commitment and one-team approach were key to our successful delivery, which has been widely recognised as such within BP."

Craig Fisher Project Engineer BP Sharjah Project
Craig Fisher Project Engineer BP Sharjah Project

Key Project Achievements

  • Excellent health, safety, security, and environment performance
  • One-team approach with the client 
  • Smooth and safe changeover to the new system
  • Project installation and start-up to schedule
  • High level of system integrity, reliability, and quality management
  • High level of customer satisfaction

Central control room
Central control room

<System Details>

Integrated control and safety system: CENTUM VP
Number of hardwired I/O: 1,500
Number of serial I/O: 2,500, 32 subsystems
Number of cabinets: 14 (including 8 extensions to existing cabinets)
Number of graphics: 100
System distributed across two local equipment rooms and a central control room

System information:
6 x FCS, 1 x ENGS, 4 x HIS,
1 x Exaquantum (server for interface to MIS)
1 x large LCD (52" HD)

行业

  • 上游

     上游行业包含海上和陆上活动,包括井口自动化、分馏、完井和分离,回收和制备地下或水下原油和天然气

    当石油被带到地表时,在运输之前必须将其分离。在三相分离中,一级和二级分离阶段通常分布有气体流量、水流量和油流量。气体的输送需要管道,并且在输送之前的上游阶段需要进行分馏。液体需要通过罐和管道输送并处理,这就需要精确的液位测量

    更多

相关产品&解决方案

  • 切换规划和实施

    通过精心规划和实施,横河电机可以帮助客户系统实现安全、经济、增值的冷热切换迁移过程。

    更多
  • 创新的MAC服务

    横河电机的主要自动化承包商(MAC)服务提供全方位的项目执行能力。横河电机负责项目中所有和自动化相关的方面,帮助您满足预算、时间、人力、交付和风险管理需求。

    更多
  • 数据记录系统(Exaquantum)

    Exaquantum可以从过程工业的各个方面获取过程数据,并转换为易用、高价值、广泛发布的信息。Exaquantum是横河电机大多数OES的基础。

    更多
  • 集散控制系统(DCS)

    横河电机的集散控制系统(DCS) 可实现工业过程的自动化和控制,并提高业务绩效。30,000多套系统的经营者选择采用横河电机的DCS来实现其生产目标。

    更多

置顶
WeChat QR Code
横河电机(中国)有限公司