Executive Summary

Chevron, Cape Town, South Africa
Chevron, Cape Town, South Africa

Chevron entered the South African market in 1911 and now markets its products there under the Caltex brand, which was created in 1936 by a joint venture between Standard Oil of California (the present Chevron) and The Texas Company (Texaco). Chevron operates a 100,000 barrel-per-day refinery in Cape Town that produces gasoline, diesel, jet fuel, LPG, and asphalt.

Chevron South Africa initiated a project to replace the existing Yokogawa CENTUM-XL process control system at the Cape Town refinery with CENTUM CS 3000 hardware and upgrade the control network to Vnet/IP.

Project Background

This project had the overall aim of ensuring the high reliability and availability of the refinery's distributed control system (DCS). The existing CENTUM-XL control system had been in use for over 15 years, leading to concerns about the rising risk of unplanned plant shutdowns and production losses as well as increased maintenance costs.

The intent was to replace the existing CENTUM-XL control stations with the latest Yokogawa CS 3000 hardware and upgrade the control network to the faster and more efficient Vnet/IP. In June 2008, Yokogawa South Africa was appointed principal contractor and given overall responsibility for the project.

Project Overview

The plan was to minimize plant downtime by doing a hot cutover from the old to the new control system, and to then immediately test all instruments and controls.

Structured and formal project and engineering procedures were developed to make sure that every process requirement would be fulfilled and all risks mitigated. The execution procedure culminated with a thorough risk assessment process that involved all key stakeholders.

To meet all of Chevron's requirements, personnel responsible for reliability and maintenance, advanced control, construction, and operations were assigned to the project.

Prior to the hot cutover of each control station, the existing system was re-configured for the CS 3000. A formal process was followed to ensure all the control logic and functionality was retained and that this complied with the software configuration standard developed for the project.

After the approval of the design, the Yokogawa CS 3000 hardware was installed in the DCS panels and the panels were acceptance tested.

The hot cutover process was carried out on an individual I/O point basis. Field wiring was transferred point by point from the old DCS to the new DCS and at the same time the existing configuration (program) was disabled and the new configuration activated. Control valves were bypassed until the controller was successfully cut over.

Success Factors

The cutover of this 100,000 barrel-per-day Cape Town refinery was performed live without disruption to production operations, and Yokogawa achieved this on time and within budget.

The following key factors contributed to this success:

  • The experience of the team members
  • Excellent teamwork between the Yokogawa and Chevron personnel assigned to the project
  • Good communication between team members during the cutover process
  • The planning and implementation of a structured and methodical approach
  • The completion of a thorough risk assessment process to mitigate all risks
  • Continual evaluation and improvement of processes based on lessons learned

Customer Satisfaction

Comment from Phillip Venter – Project Manager "There are several factors that I believe were major contributors to the success of this project. From the RFQ stage of the project there was excellent teamwork between Yokogawa and Chevron. We all shared the vision of successfully completing the project within schedule and budget, with no production loss and zero incidents.

Having the entire Yokogawa team in one location on site has drastically improved the efficiency of the team, coupled with each team member's personal commitment to the project. It sure has been a pleasure and an honor to work with the Yokogawa project team.

In any project, strength lies in the ability to adapt to the ever changing circumstances and the collective effort of continuous improvement."

Phillip Venter, Chevron
Phillip Venter, Chevron

Project Statistics

Control system upgraded to CENTUM CS 3000 Vnet/IP

Hardwired I/O cut over: 7,132
FCS's cut over: 24
I/O modules: 611
Nodes: 123
System cables: 805
Terminal boards: 499
Domains upgraded to Vnet/IP: 3
Engineering stations (EWS): 3
Human interface stations (HIS): 30
Incident free man-hours on site to date: 50,584
Number of loss incidents: 0

相关行业

  • 油气下游

    近年来,石油天然气下游行业正面临日益增多的挑战。这些挑战包括:需处理的原料特性不断变化、工艺设施与设备逐渐老化、能源成本持续攀升、能够安全高效运营炼油厂的熟练操作人员紧缺,以及市场和客户需求的快速变化。

    多年来,横河电机与众多下游企业携手合作,提供专注于解决这些挑战与难题的工业解决方案。横河电机的 VigilantPlant解决方案助力工厂业主实现工厂内的更大盈利和可持续安全运营。

  • 炼油

    在不断变化的市场环境中,炼油厂不仅被视为原油加工单元,更是利润中心。与此同时,业界对这些设施的安全需求保持着高度重视。要实现长期盈利、效率提升与环境保护的目标,需要一套涵盖规划、调度、管理与控制的完整生产解决方案。凭借在自动化领域多年的专业积淀,横河电机能够为您提供高性价比的整体解决方案,助力提升运营效能,共创更清洁的世界。

相关产品&解决方案

  • 切换规划和实施

    通过规划和实施,横河电机可以帮助客户系统实现安全、经济、增加收益的冷热切换迁移过程。

  • 集散控制系统(DCS)

    横河电机的集散控制系统(DCS) 可实现工业过程的自动化和控制,并提高业务绩效。30,000多套系统的经营者选择采用横河电机的DCS来实现其生产目标。


置顶
WeChat QR Code
横河电机(中国)有限公司