Yokogawa Successfully Completes DCS Controller Replacement Project (hot cutover)

Chevron logo
다운로드 (320 KB)

Executive Summary

Chevron, Cape Town, South Africa
Chevron, Cape Town, South Africa

Chevron entered the South African market in 1911 and now markets its products there under the Caltex brand, which was created in 1936 by a joint venture between Standard Oil of California (the present Chevron) and The Texas Company (Texaco). Chevron operates a 100,000 barrel-per-day refinery in Cape Town that produces gasoline, diesel, jet fuel, LPG, and asphalt.

Chevron South Africa initiated a project to replace the existing Yokogawa CENTUM-XL process control system at the Cape Town refinery with CENTUM CS 3000 hardware and upgrade the control network to Vnet/IP.

Project Background

This project had the overall aim of ensuring the high reliability and availability of the refinery's distributed control system (DCS). The existing CENTUM-XL control system had been in use for over 15 years, leading to concerns about the rising risk of unplanned plant shutdowns and production losses as well as increased maintenance costs.

The intent was to replace the existing CENTUM-XL control stations with the latest Yokogawa CS 3000 hardware and upgrade the control network to the faster and more efficient Vnet/IP. In June 2008, Yokogawa South Africa was appointed principal contractor and given overall responsibility for the project.

Project Overview

The plan was to minimize plant downtime by doing a hot cutover from the old to the new control system, and to then immediately test all instruments and controls.

Structured and formal project and engineering procedures were developed to make sure that every process requirement would be fulfilled and all risks mitigated. The execution procedure culminated with a thorough risk assessment process that involved all key stakeholders.

To meet all of Chevron's requirements, personnel responsible for reliability and maintenance, advanced control, construction, and operations were assigned to the project.

Prior to the hot cutover of each control station, the existing system was re-configured for the CS 3000. A formal process was followed to ensure all the control logic and functionality was retained and that this complied with the software configuration standard developed for the project.

After the approval of the design, the Yokogawa CS 3000 hardware was installed in the DCS panels and the panels were acceptance tested.

The hot cutover process was carried out on an individual I/O point basis. Field wiring was transferred point by point from the old DCS to the new DCS and at the same time the existing configuration (program) was disabled and the new configuration activated. Control valves were bypassed until the controller was successfully cut over.

Success Factors

The cutover of this 100,000 barrel-per-day Cape Town refinery was performed live without disruption to production operations, and Yokogawa achieved this on time and within budget.

The following key factors contributed to this success:

  • The experience of the team members
  • Excellent teamwork between the Yokogawa and Chevron personnel assigned to the project
  • Good communication between team members during the cutover process
  • The planning and implementation of a structured and methodical approach
  • The completion of a thorough risk assessment process to mitigate all risks
  • Continual evaluation and improvement of processes based on lessons learned

Customer Satisfaction

Comment from Phillip Venter – Project Manager "There are several factors that I believe were major contributors to the success of this project. From the RFQ stage of the project there was excellent teamwork between Yokogawa and Chevron. We all shared the vision of successfully completing the project within schedule and budget, with no production loss and zero incidents.

Having the entire Yokogawa team in one location on site has drastically improved the efficiency of the team, coupled with each team member's personal commitment to the project. It sure has been a pleasure and an honor to work with the Yokogawa project team.

In any project, strength lies in the ability to adapt to the ever changing circumstances and the collective effort of continuous improvement."

Phillip Venter, Chevron
Phillip Venter, Chevron

Project Statistics

Control system upgraded to CENTUM CS 3000 Vnet/IP

Hardwired I/O cut over: 7,132
FCS's cut over: 24
I/O modules: 611
Nodes: 123
System cables: 805
Terminal boards: 499
Domains upgraded to Vnet/IP: 3
Engineering stations (EWS): 3
Human interface stations (HIS): 30
Incident free man-hours on site to date: 50,584
Number of loss incidents: 0

업종

  • 오일 및 가스관련 다운스트림

    석유 및 가스 산업은 최근 몇 년간 어려움이 커지고 있습니다. 여기에는 처리할 원료의 변화하는 특성, 공정 설비 및 장비의 고령화, 에너지 비용의 상승, 정유 공장을 안전하고 효율적으로 운영할 수 있는 숙련 된 플랜트 운영자의 부족, 그리고 시장과 시장의 끊임없이 변화하는 요구 사항이 포함됩니다.

    지난 수년간 Yokogawa와는 많은 어려움을 겪고 있는 산업 솔루션을 제공하기 위해 여러 다운스트림 회사와 파트너 관계를 맺어 왔습니다. Yokogawa의 VigilantPlant 솔루션은 플랜트 소유자가 플랜트 내에서 최대한의 수익성과 지속 가능한 안전을 달성하도록 도왔습니다.

    See More
  • 정유

    끊임없이 변화하는 시장에서 정유설비는 원유 처리 장치뿐만 아니라 이익센터로도 인식됩니다. 동시에 그러한 시설에서 안전의 필요성에 대한 각별한 인식이 있습니다. 계획, 스케줄링, 관리 및 제어를 포함하는 총 생산 솔루션은 수익성, 효율성 및 환경 보호를 위한 장기 목표를 달성하는 데 필요합니다. Yokogawa는 자동화 분야에서 수년간 축적 된 전문성을 바탕으로 보다 향상된 작업성 및 보다 깨끗한 세상을위한 효율적인 솔루션을 제공합니다.

    See More

Related Products & Solutions

  • 컷오버 계획 및 실행

    신중한 계획과 실행을 통해 요꼬가와는 고객의 시스템을 안전과 합리적인 비용, 가치를 더한 마이그레이션 프로세스를 실현 할 수 있도록 도와줍니다.

     

    See More

Top