CACT Offshore Platform Reduces Unplanned Downtime by Migrating from Legacy PLC System to Reliable CENTUM CS 3000

CACT Operators Group logo
다운로드 (362 KB)

Executive Summary

CACT Operation Group
CACT Offshore Platform Reduces Unplanned Downtime by Migrating
from Legacy PLC System to Reliable CENTUM CS 3000

The Hui Zhou 21-1A (HZ21-1A) offshore gas production platform has been operational since 1990. It is in the South China Sea, 130 km south of Shenzhen, China, and the water depth at this location is approximately 115 meters. The HZ21-1 gas field is operated by CACT Operators Group (CACT), a joint venture between CNOOC Ltd., Eni China BV, and Chevron Corporation. Four wells in this field produce 54 million cubic feet of natural gas per day. After processing, this gas is piped to a natural gas terminal in Zhuhai through subsea pipelines.

In 2004 CACT began construction of the HZ21-1B platform to house facilities for the compression and dehydration of gas. Now completed, this platform is positioned near HZ21-1A, and a bridge has been built to link the two platforms.

As part of its ongoing activities to develop the HZ21-1 gas field, CACT has also made modifications to HZ21-1A. This included the migration from a legacy PLC control system – for which spare parts were no longer available – to Yokogawa's CENTUM CS 3000. CACT's principle aim in this was to improve efficiency and productivity by acquiring the ability to monitor and control production data in real time. A further benefit of this migration was that the new production control system could be integrated with the control system on the new HZ21-1B platform, allowing HZ21-1A to convert to unmanned operations.

Yokogawa Engineering Asia and the CACT project team worked closely with Aker Kvaerner in Singapore and the China Offshore Oil Engineering Corporation (COOEC) to ensure smooth execution of this project. All systems and products were delivered to the COOEC construction yard in Tongu, China ahead of schedule.

The Challenges and the Solutions

Challenge 1
Maintenance is a big issue on all offshore platforms. Maintaining equipment which is located hundreds of kilometers from shore can be costly and time consuming. Unanticipated equipment failures can quickly lead to platform shutdowns costing millions of dollars in lost production. The various Yokogawa systems and products including the CENTUM CS 3000 have proven to be highly reliable and have caused no unplanned shutdowns, providing major cost savings for CACT. This has also eliminated various safety and environmental risks.

Challenge 2
The HZ21-1A platform operations management team required the collection of key process and production data for transmission to the Zhuhai gas terminal via a satellite communications system. Accurate real-time measurement of production data is essential for the management of gas distribution. The data gathered by the monitoring and control system can also be used to detect gas leaks in the pipeline.

Challenge 3
CACT's process control and instrument engineers are responsible for keeping down the cost of configuration changes to the control system. With the CENTUM CS 3000, it is possible for CACT engineers to modify the system configuration, download software updates, and hot-swap I/O cards while the process control system is online.

Challenge 4
CACT places a high priority on protecting the environment. For example, after removing water that has been produced by a separator, the company treats it to bring it up to government standards before discharging it. The pH and conductivity levels are accurately measured by Yokogawa's analytical instruments, which are linked with the control system so that alarms can be issued and the water treatment system shut down if set limits are exceeded.

Customer Satisfaction

"Yokogawa's reliable, proactive, and responsible approach made a significant contribution to the project's success. The positive and cooperative approach of your team facilitated teamwork and good relationships. We commend your project team for this great effort and look forward to working with you in the future."

David Godard, HZ21 Gas Project Manager

Factory Acceptance Test

CENTUM CS 3000

CENTUM CS 3000

ESD console

ESD console

CCTV

CCTV

HZ21 Project – System Configuration

The new control system designed and built by Yokogawa for CACT's HZ21 gas field project consists of the following sub-systems and components:

CENTUM CS 3000 platform process control system
ProSafe PLC safety shutdown system and fire & gas system
FieldEye CCTV system
Local area network
Satellite communications system consisting of a satellite dish, ODU, VAST modem & router, PABX telephone system, and PAGA system

업종

  • 업스트림

    업스트림(Upstream) 산업에는 유전 또는 해저의 원유 및 천연가스의 채취 및 생산을 위한 유정제어, 증류, 분리 및 제품 완성을 포함한 해상 및 육상 플랜트가 포함됩니다.

    석유는 육상으로 옮겨져야 하는 관계로 운송 전에 분리 작업이 필요합니다. 1차 및 2차 분리 단계는 일반적으로 가스 흐름, 물 흐름 및 오일 흐름의 3단계로 분류됩니다. 가스 이동은 파이프라인을 필요로 하며, 이동하기 전에 상류 공정에서 분류 공정을 거치게 됩니다. 액체는 탱크 또는 파이프라인에 넣고 운송을 하므로 정확한 레벨 측정이 가능한 레벨계가 필요합니다.

    See More
  • 오일 및 가스

    Yokogawa는 해상 및 육상 시설에서 파이프라인, 터미널 및 심해 운전에 이르기까지 석유 및 가스 사업의 모든 부분에서 풍부한 경험을 보유하고 있습니다. 우리는 안전을 강화하고 정확하고 신뢰성 있는 운전을 보장하며 플랜트 효율을 높이는 솔루션을 제공합니다.

    See More

Related Products & Solutions


Top