Ensuring Safe and Reliable Operations of Power Generation Units and Steamfields at PT PLN & PT Pertamina Geothermal Energy, Lahendong, Indonesia

PT PLN and PT Pertamina Geothermal Energy (PGE) logo
다운로드 (360 KB)

Executive Summary

PT PLN is a government-owned company that manages the electric power industry in Indonesia, while PT Pertamina Geothermal Energy (PGE), also a government-owned company, develops geothermal steamfields. To ensure a stable power supply for North Sulawesi province, PLN and PGE have jointly built and are currently operating six geothermal power plants in Lahendong, which is located 30 km south of Manado, the provincial capital. 

Indonesia’s population and economy are growing at a remarkable rate, and the country’s demand for electricity far outstrips supply. Despite holding 40 percent of the world’s geothermal reserves, enough to produce about 30,000 MW, the country has done relatively little till now to make use of this resource. However, the Indonesian government has signaled a strong intention to begin developing the country’s geothermal resources.

Geothermal energy is a clean and renewable power source, and plants of this type produce extremely little CO2, which is a major contributor to the greenhouse effect. For this reason, efforts to make use of this resource are gaining momentum, and its development is expected to bring great environmental and economic benefits.

At the Lahendong III geothermal power plant, Yokogawa installed the CENTUM CS 3000 distributed control system (DCS) with redundant controllers, a backup system, and a test system in 2008. Based on the success of these installed systems, Yokogawa subsequently received an order to install its CENTUM VP DCS at the Lahendong IV geothermal power plant in 2010.

Then, when carrying out projects to renovate the Lahendong I and II plants, PT PLN selected the CENTUM VP to replace the existing Bailey INFI 90 system that had been used to monitor and control the steam turbine auxiliary facilities as it was approaching the end of its useful life. The solid performance of the systems used, combined with Yokogawa's superior technical expertise in geothermal power generation, the proven quality of its products, and its extensive engineering and service network in Indonesia, were primary considerations in PT PLN's decision to go with the CENTUM VP solution again.

 

The Challenges and the Solutions

Automated plant and turbine startup and shutdown

Plant and turbine startup and shutdown procedures are very complex and time-consuming, and place great stress on both personnel and equipment. To eliminate operator errors during these critical processes, the CENTUM DCS has automated plant and turbine startup and shutdown procedures. The startup and shutdown sequences are executed in accordance with the logic design, and the DCS human machine interface (HMI) clearly shows the status of the sequence and the facility conditions. It also guides operators in the acknowledgement of messages and alarms and the triggering of interlock sequences. Operator intervention during the automated plant and turbine startup and shutdown processes is minimized, ensuring safe and smooth startup and shutdown. This greatly reduces operator workload and errors, shortens the startup and shutdown times, and mitigates thermal and physical stress on the turbine.

Backup system

Geothermal power plants have less auxiliary equipment and their control loops are not as complex as those at fossil fuel power plants. In addition, they cost less to operate. It is therefore feasible and desirable to run a geothermal power plant nonstop at full load. When a plant is operated in this way, reliability is a key concern. And even when the plant’s DCS has redundant controllers and is extremely reliable, there is still a risk that it might fail in a corrosive environment. For this reason, Yokogawa has provided a backup system. This backup system includes the following features:

  • Monitors by using a graphical user interface to ensure safety operation while the backup system is engaged
  • Handles effective alarms
  • Performs emergency operation in the event that the DCS fails

The backup system ensures that the plant can run safely without any interruptions.

Sequence-of-events (SOE) station

All events are precisely recorded with millisecond accuracy and displayed in a sequence of events (SOE) window for later analysis. Using this, operators can assess the cause of any problem and request a fix by maintenance personnel.

Test system

When application software needs to be modified, the revised software must be tested before it can be downloaded to the controller, requiring a plant shutdown. To maximize plant uptime, Yokogawa provided a test system that uses the test functions of the CENTUM CS 3000. This test system accurately replicates the plant control and graphical interfaces, and the software can be easily checked under the same conditions as with the actual plant system. It can be also used to train the operators.

PT PLN and PT Pertamina Geothermal Energy (PGE)

 

Customer Satisfaction

The design and structure of the CENTUM CS 3000 and CENTUM VP systems for these geothermal power plants exceeded PT PLN’s high expectations. The use of the same HMI in both systems allows for complete consistency in the monitoring and control of the power plants and turbines at both plants. PT PLN greatly appreciates having the ability to automatically execute flawless plant and turbine startups and shutdowns.

In 2020, PGE selected Yokogawa’s CENTUM DCS to replace the existing control systems for its steamfield above ground system (SAGS) in Units 1-4. When this project is completed, both the SAGS and the power generators of Units 1-4 of the plant will be controlled by Yokogawa’s systems. The newly integrated system will maximize the potential of Industrial-Internet-of-Things devices when introduced, boosting productivity and efficiency.

Furthermore in 2021, PGE chose Yokogawa for the procurement of a 500-kW binary organic rankine cycle (ORC) power plant to be connected to the SAGS of Lahendong Units 1-4. The plant is scheduled to be commissioned at the end of the same year. This will increase the efficiency of power generation in the Lahendong area since the power produced using excess brine (hot water) from the reservoir will be used for the SAGS instead of using electricity generated from Units 1-4. The success of this project will incentivize the development of renewable energy in the country. PT PLN is looking forward to further collaboration with Yokogawa.

 

업종

  • 신재생에너지

    신재생에너지의 사용은 환경을 보호하고 사회와 산업 모두를 지속 가능한 사회를 만드는 목표를 달성하는 데 도움이 됩니다. 그러나 기존의 에너지원에 비해 생산 원가 상승과 그리드 전력 공급 불안정과 같은 급속한 채택에 직면하는 특정 문제가 있습니다. Yokogawa는 제어 및 계장 사업의 선도 기업으로서 다양한 산업 분야의 고객이 안정적인 운영을 달성하고 공장의 생산성을 향상시키도록 항상 노력해 왔습니다. 운영 효율성을 달성하기 위한 VigilantPlant 개념을 기반으로 우리는 신재생 에너지원의 사용 방법을 제시하는 솔루션을 제공하고 있습니다.

    See More
  • 지열발전

    지열에너지는 기상 조건에 의존하지 않기 때문에 일 년 내내 안정적인 전력을 공급할 수 있습니다. 또한 어떤 연료도 지상에서 태우지 않으며 매우 적은 양의 이산화탄소만 배출되므로 환경친화적입니다. 태평양, 일본, 필리핀, 인도네시아, 뉴질랜드, 멕시코, 코스타리카, 미국 등의 국가에서 태평양 연안 벨트 ("불의 고리"라고도 함)를 따라 풍부한 지열 자원이 있습니다. 다른 지열 활동 지역에 위치한 아이슬란드, 터키 및 이탈리아와 같은 국가들과 협력합니다. Yokogawa는 현재까지 일본, 동남아시아 및 기타 지역의 30개 지열발전 프로젝트를 실행한 경험을 바탕으로 지열발전 시스템의 신뢰성 및 유지 관리 효율성을 향상시키는 다양한 측정 및 제어 기술을 제공하고 있습니다.

    See More

Related Products & Solutions

  • CENTUM VP

    CENTUM VP는 HMI(Human Machine Interface), FCS(Field Control Stations), 제어 네트워크(Control Network)로 구성된 단순하고 일반적인 아키텍처를 가지고 있습니다.

    See More

Top